Traffic block between Ghagwal - Samba Section on 12th & 13th January, 2017

To carry out the work of placing of 400 KV two numbers of overhead electric crossings o­n Pathankot- Jammu Tawi double line, a 3 hrs Traffic block will be under taken o­n UP & DOWN lines between Ghagwal & Samba section at km 60/0-1, from 12.00 hrs to 15.00 hrs o­n 12thJanuary, 2017 & 13th January, 2017.

          During the block period, the traffic will be affected as follows:

·Following train will be Regulated:-

1.Train no. 12471 Bandra Terminus- Shri Mata Vaishnodevi Katra Swaraj Express of 12thJanuary, 2017 will be regulated between Kathua & Samba section for 1.30hrs.

2.Train no. 12475 Hapa- Shri Mata Vaishnodevi Katra Express of 11th January, 2017 will be regulated between Kathua & Samba section for 1.30hrs

To carry out the work of placing of 400 KV two numbers of overhead electric crossings o­n Pathankot- Jammu Tawi double line, a 3 hrs Traffic block will be under taken o­n UP & DOWN lines between Ghagwal & Samba section at km 60/0-1, from 12.00 hrs to 15.00 hrs o­n 12thJanuary, 2017 & 13th January, 2017.

          During the block period, the traffic will be affected as follows:

·Following train will be Regulated:-

1.Train no. 12471 Bandra Terminus- Shri Mata Vaishnodevi Katra Swaraj Express of 12thJanuary, 2017 will be regulated between Kathua & Samba section for 1.30hrs.

2.Train no. 12475 Hapa- Shri Mata Vaishnodevi Katra Express of 11th January, 2017 will be regulated between Kathua & Samba section for 1.30hrs